November 2025 Update
Activity date

On 10th November 2025, the CMU-Ganol Engineers along with the Water Resources Department team led by Shri. Bilseng Sangma, JE, and the Sectional Assistant of Rongram Block, conducted a joint site verification visit to Durakalakgre, Rengsangre, and Jendragre villages. A total of seven sites were inspected, out of which three were found feasible for implementation.


Jendragre VPIC: Two proposed sites were found not feasible.
Rengsangre VPIC: All three proposed sites were found feasible.
Durakalakgre VPIC: Two proposed sites were found not feasible.


Reasons for non-feasibility is due to Presence of existing structures, Seasonal nature of water sources, Proximity to main road and Limited household benefit